Monday, August 29, 2011

SURPRISE SURPRISE, CORPS PLAN NOT WORKING AGAIN

What we've been saying for some time is now obvious. The "management plan" in use by the US Army Corps of Engineers does not work and has not for many years now. There is a saying that accurately explains our situation. THE HEIGHT OF INSANITY IS TO CONTINUE DOING THE SAME THING OVER AND OVER AGAIN EXPECTING THE RESULTS TO CHANGE. If you have any input to the Corps please see if you can get them to listen to reason because our best efforts to get them to heed our warnings have failed up to now.

The Corps has failed to live up to one of the 7 responsibilities they have in managing Lake Thurmond. Once the lake drops 6' recreation is badly damaged. What is so disconcerting is that the Corps could have dropped release rates to 3600cfs back when the lake level started falling and we would be at full pool. The only responsibility that would be impacted by such a change is power production but this is more than offset by avoiding damage to the economy around the lake. The Corps insists that economics is not one of their responsibilities but such a claim is ludicrous. First the only defense for holding power production at the expense of lake level is the economics of buying more expensive power elsewhere. But if you compare the savings in power costs to the economic losses around the lake, increased power cost is dwarfed by eonomic losses. In other words it is my opinion that the responsibility concerning power production is strictly an economic one which defeats the Corps claim of no responsibility in that arena. There are other arguments why power production should not be put ahead of recreation and economic concerns:
Thurmond is a peaking power source. As such it is much better to have a full lake when high demand hits than to have the lake at a greatly reduced level and be unable to provide peaking power.
Hydro power is desirable because it is a renewable energy source. But if you are releasing more water to produce power than is coming to the basin from rain it is no longer a renewable energy source.
In summary if the Corps would make a simple change to their drought plan all the problems we repeatedly experience from severe droughts could be avoided and all responsibilities the Corps has would be met without any problems except for possible temporary reductions of power production. These temporary reductions in power reduction would cost far less than the economic damages done around Lake Thurmond with the current drought plan.

Jerry Clontz, Spokesman for Save Our Lakes Now

Monday, August 22, 2011

CORPS NEEDS MATH LESSON

Since July of 2010 the Corps has released an average of 5038 cfs from Lake Thurmond. During this same period Save Our Lakes Now has pleaded with the Corps to use a release rate of 3600cfs anytime the lake is below 328'. Most people do not realize but the difference between 5000cfs and 3600cfs over a years time is 14' of elevation. In other words all the Corps had to do was use 3600cfs intermittently over the past year and our lake would still be full.

Wednesday, August 17, 2011

Corps Claims "Just Following Orders"

The whole Savannah River Basin is in jeopardy and we have answers on how to correct this situation but the Corps is hiding behind the excuse that they do not make policy. As we all know "just following orders" is not an acceptable excuse for acts that bring about destruction. We need congressional help or public exposure to get the Corps to listen to reason.

We have presented plans numerous times that prevent the destruction of recreation and economics when the lakes drop too low while at the same time protecting downstream interests by providing river flows that have been demonstrated to be acceptable. Rather than explore this approach the Corps spent huge amounts of time and money to develop a way to literally drain the lakes which would totally devastate the areas upstream of the dams.

Several things show the current approach in use by the Corps is not ligical:
1.rather than balance water releases with what is supplied by rain the Corps follows a release plan that bankrupts the system during droughts and runs the risk of destroying the whole Savannah River System
2.they literally throw fresh water to the ocean during severe droughts when fresh water becomes precious. .
3.they call hydropower a renewable power source but it is renewable only if you limit the water used to that which is supplied by rain.
4.they ignore demonstrated destruction of recreation and economics upstream of the dam in favor of possible imagined problems downstream.

Right now today the Corps is allowing the lakes to drop drastically and the levels will soon be destructive to recreation and economics. We have pleaded with them to drop release rates to 3600cfs which is acceptable downstream but they are holding them at 4200cfs. In a years time 4200 cfs puts Thurmond 6' lower than it would be at 3600cfs. The area went through a massive drought in 2008 which destroyed the economics of the region. This drought could be even more destructive because of its proximity to the one of 2008.