Tuesday, April 19, 2011

Drought Management Plan for Lake Thurmond

For the purposes of this post I am presenting my idea of the ideal drought plan for Lake Thurmond . Treating the operation of the dam as a standard engineering problem it really is quite simple.




1) Keep lake levels at full pool to within a few tenths of a foot as long as there is enough rain to do so. This capability has been demonstrated by years of balancing Lake Hartwell vs Lake Thurmond.




2) When release rates drop to 3600cfs allow the lake level to fall until rainfall permits maintaining a full pool again.




3) As part of maintaining lake levels as close to full pool as possible river flows following a rain event should be monitored to allow dropping below 3600cfs when possible.




The philosophy behind this plan is that all parameters the Corps is charged with for the Savannah River Basin can be maintained as long as there is plenty of water in the lake to give acceptable river flows. In the past lake levels have been permitted to drop with low rain fall. The trigger points for reducing releases from Lake Thurmond Dam were too low and the release rates called for allowed the lake to continue dropping too long. Had the drought of 2008 continued a little longer we could have lost the whole basin. This is simply unacceptable.




The biggest objections I have run into to date with this proposal is whether 3600cfs is adequate for downstream needs. I picked this figure for the following reasons:


1) no downstream stakeholders had any problems from a 3600cfs release rate that continued for over 12 consecutive. That being true why not use 3600 unless some problem rears its head or until more detailed studies can be completed.


2) the industrial release limits along the Savannah River are based on 3600cfs.


3) 3600 appears to be adequate for the Short Nosed Sturgeon.


4) detailed analyses of oxygen demand along the Savannah since 1977 show that reducing releases to 3600 in 2008 had no deleterious affect on oxygen level at Clyo which means no effect on the harbor either.




Downstream stakeholders will probably interpret this plan as selfish interests by lake stakeholders. In reality though this is the only way to protect downstream interests from being devastated should lake levels drop so low that adequate river flows can no longer be maintained. Looking at the parameters the Corps has been charged with (flood control, hydro power, navigation, recreation, water quality, water supply, fish and wildlife, economics) this is the only way to meet all these. With the current drought plan recreation and economics are destroyed quickly in a drought. All the other parameters are lost if you ever reach the bottom of the conservation pool.




Some will argue that hydropower is lost but SEPA has repeatedly assured us and the Corps that they want the lakes to be as full as possible. From their perspective they can reduce power production and spread the burden on others without any major problems. What would devaste SEPA would be lake levels so low they can no longer produce power.




This plan will work equally well if we decide some higher release rate has to be maintained. Simply insert that release rate into the equation and the rest remains unchanged.

Monday, February 7, 2011

REASONS TO NOT REDUCE THURMOND RELEASES BASED ON DISTORTIONS OF THE TRUTH

If you've followed my blog for any time you realize we are not making exaggerated claims for better management of Lake Levels at Lake Thurmond. Our basic reasoning is that the Corps can not create water and until they are able to do so lake releases should match lake input from rain or you run the risk of destroying the lake. Our recommendation is to balance input with output by reducing releases to the average annual input that occured in the drought of record in 2008 anytime Lake Thurmond drops 2' below full pool. Using this approach reduced flows last only for a minimum amount of time since the lake refills quickly. Furthermore the river flows that occur at this release rate were demonstrated during the drought of 2008 to be acceptable for downstream stakeholders.

Since this meets the needs of both the people downstream and the ones around the lakes and since it avoids the armageddon effects that occur if you drain the lake below the conservation pool, you'd think a reasonable person would agree to our suggestions. Not so with the Corps and government environmental interests.

The Corps talks about percentage of storage that has to be dedicated to different things as if they can create water out of thin air. If you release all the water percentages no longer count. And if you release more water than nature provides from rain this will eventually occur.

Environmental concerns have been grossly exaggerated by both the Corps and government environmental agencies. For example mention has been made that short nosed sturgeon spawning in the Augusta Shoals MIGHT be impacted by low flows. But sturgeon can not reach the shoals because of the lock and dam. Concern has been expressed about needing sufficient flows to keep dissolved oxygen in limits and to push back against Atlantic tidewaters to protect drinking water against salt intake. In talking with representatives of the Savannah Water Department they state neither salt water intrusion nor dissolved oxygen are a problem now or in the past and logic dictates that the Savannah River is helpless in fighting back Atlantic tides. Environmental interests claim there is too little data to know for sure that this fish or that mussel etc. etc. might be impacted. They fail to consider that artificial river flows averaged out to avoid major fluctuations are far superior to what fish and wildlife had to survive when there was no dam. Still other imaginary concerns voiced by some environmentalists have been lack of high flows affecting sturgeon in the river and the tiger lilly in the shoals. Studies in 2004 indicate that cold water temperatures from high flows drive sturgeon away and recent studies by Augusta University show high flows are destructive to the tiger lilly in the Shoals.

Many demands by environmental groups show a total lack of logic. Claims have been made for much higher flows to benefit waste dilution and/or fish and wildlife. Wanting more water does not make it magically appear. Somehow we've got to get across that you only have so much water based on how much nature provides. If you release more to the ocean than you get from nature you will destroy the whole system and all the fish and wildlife and other environmental concerns along with it. The concern by environmetal groups that we are somehow hoarding the water for use in the lakes is unfounded. We send every drop mother nature provides downstream. We don't keep a single drop.

Saturday, January 1, 2011

TIME FOR ACTION HAS COME

The Corps has made it clear that they do not intend to get away from the current drought plan which has almost destroyed the Savannah River Basin several times. Basically the problem is they bankrupt the system by "spending" more water than nature provides during a drought. We've asked the Corps by who's authority they are sending more water to the ocean than is provided by mother nature. We've not gotten a response. We feel certain there is no such authorization.

If you look at the five lakes other than the Savannah River Basin in this drought footprint, they are all within 2ft of full pool. Our lakes are down over 6ft. Even Lake Lanier is within 2ft of full. Hence the drought is not the reason our lakes are low. Rather it is the Corps' management of water releases from Thurmond Dam.

If you talk to the Corps they will explain that the sturgeon need so much water, the city of Augusta needs so much, there is dissolved oxygen to consider, etc. etc. What they fail to mention is that these needs can only be met as long as we have lakes with water in them. If we exhaust these lakes none of these needs can be met. What they also fail to mention is that we ran a 14 month test in which releases were held to that coming in from rain and everyone's needs downstream were met including the sturgeon.

We also learned recently that the Corps has a plan to destroy the lakes one at a time (Russell first, then Thurmond, etc.) if a drought lasts long enough to make it impossible to make the releases specified in their current plan. It makes a lot more sense to match the rain fall over a years time and never come to such an Armageddon type situation.

A new advisory council was set up recently for input to the SC DNR and DHEC by a representative group of stakeholders that represent all Savannah River Basin interests from the mountains to the sea. I have submitted a request to this group to consider the current drought plan at their next meeting and formulate a recommendation on how the current drought plan should be modified.

In view of what a few people in the Tea Party were able to accomplish in the last election, we can get this changed. If the newly formed SRBAC can not help we can simply raise our voices until we are heard. You will be hearing more on this in the near future.

Saturday, December 18, 2010

PROGRESS ON IMPROVING DROUGHT PLAN HAS COME TO A STOP

Several months ago a new commander took control of the Savannah River Basin. That and setting up the Savannah River Basin Advisory Commission (SRBAC) gave hope that we might finally be making progress in the way lake levels are managed during droughts. After years of trying to get the Corps to stop releasing more water than that supplied by nature, two way communication was actually happening. In meetings around the state the Corps acknowledged that they had full latitude to change release rates to match annual input from rain. They even spoke about decreasing releases still further when the river below Thurmond Dam is swollen from rains. Now all of these measures have come to a stop. Now instead of open and honest expression of what needs to change everyone seems to have reverted to a politically correct type position. Whether it is discussions at the SRBAC or talking to the Corps
we are back to the old story of "the corps can't deviate from the written drought plan without a huge amount of study, temporary approvals of everybody, etc. etc.". In other words we have returned to square one and all our "breakthroughs" have been shoved under the table. The timing was coincident with but not necessarilly caused by the ridiculous claims of the Clemson Economic Study claiming the major drought of 2008 had very little impact on the economics of the region.

Claims of a need for further study make no sense. All the flows involved with the recommended changes to the drought plan have been fully tested with no ill effects and as noted above the Corps has even told us that they have full latitude for such a change. At the very least it makes more sense to use a plan that works on a temporary basis until everyone can approve the plan formally. It makes no sense to continue using a plan (even on a temporary basis)that has failed repeatedly and almost caused us to lose the whole basin.

The logic behind the changes we are recommending the Corps use is simple. Hold release rates to the annual rate of rainfall during a drought anytime Lake Thurmond drops 2' from full pool. Past modeling of the Savannah River Basin showed that such a measure would keep the lake levels from dropping more than about 6 ft. The timing of starting these release rates is important because the lake can drop 6' from the point where the releases are reduced. Currently the Corps has allowed Lake Thurmond to drop 6 to 7 feet without dropping the release rate to the level recommended. A drop of another 6 ft would put us in the same territory as 2008 when we were down over 15'.

We know from what the Tea Party did that we can get this right if enough people get behind it. Unless something changes quickly we will be seeking the help of all stakeholders around the lakes. When the time comes please help us with emails and phone calls to your congressmen, the Corps, and your representatives on the SRBAC. Also, we only have a limited list to notify of this so when we contact you please make sure to inform everyone you know who has an interest in how our lakes are being run so we can increase our numbers. You should hear further from us in early January as to what we need to do.

Tuesday, December 7, 2010

HANDOUT PREPARED FOR SRBAC 12/8 MTG IN BEAUFORT

This handout was prepared for and discussed at the 12/8 meeting of the Savannah River Basin Council in Beaufort, sc on 12/8. It summarizes our feelings on the flawed economic impact study recently done by Clemson University. I think you will find it to be a concise answer to their findings which we feel drew an incorrect conclusion about the impact of droughts on the economy of the lakes of the Savannah River Basin which include Lake Thurmond.

CONCERNS ABOUT CLEMSON ECONOMIC STUDY


1. No one who experienced the devastation to docks and shorelines in 2008 will agree that the economic impact was minor. Neither will those who depend on the lakes for their work such as marina owners, dock builders, lake side developers, etc.
2. It is not surprising that people who live in the 6 county area because of their commute to work or proximity to family suffered no impact from the drought. This is like saying no one in Columbia or Rock Hill were impacted by what happened on Lake Hartwell. The only impact is going to be on people who are in the area because of the lake. So far as I can tell there was no attempt to measure the size of this group or to look at the impact incurred by them. In my opinion the study should have been aimed at lake stakeholders and the impact on them rather than the general population.
3. The study assumes a rapid return to normal lake levels with a corresponding return to normal lake property values, etc. The major economic impact is not short term. Instead the major economic impact is loss of confidence in lake level control long term. People who move to the area because they are attracted to the lakes will stop coming, property values will suffer permanent damage on a large scale, and developments depending on the attraction of the lakes will cease. From a personal perspective I know of huge developments that are now abandoned or put on hold around Lake Thurmond because of lost confidence in lake level control.

If the purpose of the study was to determine how hardy the economy of 6 SC counties was during 2006-8 it was a success. But if the study was to look at the economic impact of low lake levels it failed to measure the variables necessary to draw a conclusion. In order to study the economic impact of low lake levels one needs to first identify the community affected by lake levels, second the impact of short term low lake levels on that community and third and most important the long term impact of low lake levels on that community. I can assure you from just looking at the magnitude of impact from lost real estate values the economic impact is not small.

Sunday, November 21, 2010

HISTORY OF CORPS MISMANAGEMENT OF LAKE THURMOND

Stakeholders around Lake Thurmond and the other lakes of the Savannah River Basin are being given the short end of the stick by the Corps. In previous droughts while our lake was being destroyed aesthically by drastic drops in level we pleaded with the Corps for a better approach to managing lake levels. I guess we sounded like a bunch of spoiled brats demanding their way. And to a certain extent we were selfishly seeking better level control for our own interests.

The Corps spoke out authoritatively about how they had to live up to certain demands by congress and were helpless to accomadate our requests. It even sounded like they were right because power generation, dissolved oxygen levels, spider lilly extinction, endangering the short nosed sturgeon, etc. etc. all sounded very plausible.

Then we started delving into each of these concerns ourselves to see if anything had been overlooked that might permit better level control. As we did we found out that there is plenty of water to meet all these demands. Rainfall, even during the worst drought on record, was enough to take care of all the Corps concerns if they would simply adjust the amount of water released annually from the dam to the amount that comes down from rain over a years time. We then proposed the Corps do just that and decrease flow from the dam to match annual rainfall rates anytime the lake is down 2 ft. This simple measure would prevent the lake from dropping more than 8 ft from full pool and if they would drop flows a little more during the cold months we could keep the lake from dropping more than 4 or 5 ft. This is where the recommndation for releases of 3,600cfs (3,100 during colder months) anytime the lakes are down more than 2 ft came from.

The Corps has turned a deaf ear to our recommendations. And they have no way to justify their position. None of the reasons for not decreasing flows are justifiable. Rather than manage the level better the Corps has chosen to maintain a river flow higher than that provided by nature. In doing so the Corps is creating an unanatural situation below the dam that could eventually destroy our whole system. If the drought goes on long enough it could mean we are no longer able to provide adequate water for Augusta and other users downstream. So this is not just a selfish concern for our interests.

No where in the stated responsibilities of the Corps is a river flow above that provided from nature justifiable. The original bases for operation of Lake Thurmond were:
1) flood control
2) hydro power
3) navigation

Later the following were added:
4) recreation
5) water quality
6) water supply
7) fish and wildlife

And in 1993 a federal court ruled that the Corps also needs to consider impact on local economics equal to these other concerns.

Maintaining an artificial river flow in excess of what mother nature provides is not required to meet any of these needs. Matter of fact operation at reduced release rates equivalent to the annual rainfall during the worst drought on record was demonstrated to meet all 8 concerns. For example fear of damaging the tiger lilly (a fish and wildlife concern) was in error. It turns out that artificial flows from the dam were damaging the tiger lilly by washing pollen off the stems prematurely and preventing natural propagation. Another example, damaging the short nosed sturgeon was found to be of no concern with the flow rates proposed. Hydro power is actually benefitted by keeping the lakes as full as possible (The South Eastern Power Association was quoted as saying they would rather reduce flows to keep the lake level high than to maintain higher flows and let the lakes drop lower. Water quality and supply are not a problem at the rates we recommended, and so on it goes. What is damaged by maintaining high artificial flows to the river the way the Corps insists is recreation and economics and the whole system is put in jeopardy of failure if the drought persists long enough.

When we discuss these items with the Corps they bring in any number of imagined problems that need to be addressed such as dissolved oxygen content of the water. But when they are proposing a project of their own that might actually drop oxygen contents (such as dredging Savannah Harbor) they simply put in artificial airation to correct the problem. And as for their excuse that they can't make changes without congresses approval, Corps management has repeatedly stated recently that they have full latitude to change flow rates if they so choose.

We are growing very tired of the lack of response from the Corps to our pleas. We need for everyone to get involved by writing the Corps and your congressman to let them know we've had enough. It's time for them to listen and quit throwing our water away to the Atlantic Ocean.

Monday, November 15, 2010

CORPS RESPONSE IN QUESTION

There are two very disturbing developments with the Corps and Control of Lake Level. First the Corps appears to have signed off on a badly flawed economic study that concluded there was only very minor impact on the economy around Lake Hartwell from the last drought. And second, with the lake dropping like a rock just like it did leading up to the last major drought the Corps is refusing to reduce release rates and close off flows from the dam when the river is swollen from rain. Such measures would help greatly with our lake levels and avoid another approach to armageddon the way we did in 2008. This is after the Corps admitted publicly that they could go to lower release rates and stop unnecesary releases at their discression.

Many leaders from the local business community have become quite concerned as well as the leadership of Save Our Lakes Now and we are reaching out to Corps leadership and our congressman for help. A letter sent today to our congressman in email form is copied below.

COPY OF LETTER SENT VIA EMAIL TO STAFF OF BROUN AND DEMINT:
Please, we need your help. The Corps of Engineers apparently is accepting an accounting report from Clemson University that is badly flawed. The study was done to determine the magnitude of economic harm caused by drastic losses in lake level during the drought of 2008. Instead of looking at economic effects of the drought such as decreased real estate values around the lake, this study looked primarily at total retail occurring in the 6 county area surrounding Lake Hartwell. This proved only that the occupants around the lake did not pack up and leave during the drought. And of course the drought, by destroying property values, made it impossible for property owners around the lake to leave. Instead they stayed and their grocery, car, movies, gas, etc. purchases remained unchanged making it look like there was no effect on the economy.

One major economic impact of lake levels is its effect on both current real estate values for lake properties and future growth from people moving into the area to enjoy the lakes. Another major loss is future developments side tracked because of fear about problems with lake levels. Marina incomes, etc. will be small in comparison. And grocery, car, movies, gas, etc. purchases for the 6 counties around Lake Hartwell is not a valid measure of economic impact of droughts.

We understand that a similar study is in progress for Lake Thurmond. A study of sales in the counties around Lake Thurmond will in no way represent the impact of droughts on this area. Real estate values for homes on the lake (there are over 4,000 properties on the lake shoreline) dropped at least $500million dollars from the drought. This is in addition to the effects of the poor economy nationwide. And there are numerous developments valued in the hundreds of millions of dollars that cannot proceed until confidence is restored in lake level control. Matter of fact huge developments that could have had a large impact on the area were cancelled in the past with fear over lake level problems given as the reason.

It is too early to know for sure but all signs point to the Corps becoming non responsive to the needs of stakeholders around the lakes. With the lake dropping rapidly the Corps is refusing to reduce release rates below those called for in the drought plan that destroyed us in 2008. This is after they have admitted they have the lattitude to decrease flows based on the experience gained in the last major drought. We were hopeful initially because they were talking about dropping releases to 3600 and 3100cfs as the weather grew cooler and they were even toying with the idea of closing off flows at the dam when the river below the dam is swollen from rains. But all that seems to have come to a halt and now the Corps is giving its blessings to the flawed economic study mentioned above.